Task Management

Start: 2025-06-01 Finish: 2025-12-15 34 Tasks Duration: 198 days Total Effort: 131.0 hours

Project Tasks
WBS ID Task Name Owner Effort (h) Dur. (d) Start Date End Date Dependency % Compl
1
Project Initiation
Sarah Chen 6.0 2.0 Jun 1 Jun 3 - 100%
1.1
└ Define Project Objectives and Scope
Sarah Chen 4.0 0.5 Jun 1 Jun 2 - 100%
1.2
└ Identify Stakeholders and Roles
Sarah Chen 1.0 0.5 Jun 2 Jun 2 - 100%
1.3
└ Develop Project Charter
Sarah Chen 1.0 0.5 Jun 3 Jun 3 - 100%
2
Project Planning
Sam Chen 35.0 16.0 Jun 4 Jul 1 - 100%
2.1
└ Develop Detailed Project Plan and Schedule
Sam Chen 2.0 1.0 Jun 4 Jun 4 1.3→ (FS) 100%
2.2
└ Financial Analysis and Incentives Research Planning
Margaret Ledger, CPA 1.0 5.0 Jun 4 Jun 11 1.3→ (FS) 100%
2.3
└ Research Maintenance Costs and Potential Savings
Sam Chen 24.0 12.0 Jun 4 Jun 24 1.3→ (FS) 100%
2.4
└ Identify and Document Government Incentives and Grants
Margaret Ledger, CPA 2.0 1.0 Jun 12 Jun 12 2.2→ (FS) 100%
2.5
└ Compile Incentives and Grants Summary Report
Margaret Ledger, CPA 0.0 0.0 Jun 16 Jun 16 2.4→ (FS) 100%
2.6
└ Calculate ROI and Payback Period
Margaret Ledger, CPA 2.0 1.0 Jun 16 Jun 16 2.5→ (FS) 100%
2.7
└ Develop Contractor Selection Criteria & Research
Sam Chen 4.0 4.0 Jun 25 Jul 1 2.3→ (FS) 100%
2.8
└ Confirm Financing Options
Margaret Ledger, CPA 0.0 0.0 Jun 17 Jun 17 2.6→ (FS) 100%
2.9
└ Select Solar Company
- 0.0 0.0 Jun 17 Jun 17 2.8→ (FS) 100%
3
Project Execution
Pretty Good Solar 54.0 98.0 Jun 17 Dec 3 - 19%
3.1
└ Site Evaluation Planning
PGS 1.0 1.0 Jun 17 Jun 17 2.9→ (FS) 100%
3.2
└ Conduct Professional Site Evaluation
PGS 3.0 5.0 Jun 23 Jun 30 - 100%
3.2.1
└ Roof Orientation and Condition Assessment
PGS 1.0 5.0 Jun 23 Jun 30 - 100%
3.2.2
└ Shading Analysis
PGS 1.0 5.0 Jun 23 Jun 30 - 100%
3.2.3
└ Structural Integrity Assessment
PGS 1.0 5.0 Jun 23 Jun 30 - 100%
3.3
└ Permitting and Regulatory Compliance Planning
PGS 1.0 30.0 Jul 1 Aug 20 3.2.3→ (FS) 100%
3.5
└ Compile Site Evaluation Report
PGS 1.0 1.0 Aug 21 Aug 21 3.3→ (FS) 100%
3.7
└ Submit Permit Application
PGS 8.0 30.0 Sep 2 Oct 22 3.5→ (FS+5d) 55%
3.8
└ Schedule Installation Activities
PGS 8.0 20.0 Oct 23 Nov 26 3.7→ (FS) 0%
3.9
└ Install Solar Panels and Electrical Components
PGS 24.0 3.0 Nov 27 Dec 2 3.8→ (FS) 0%
3.10
└ Integrate Solar Power System with Utility
PGS 8.0 1.0 Dec 3 Dec 3 3.9→ (FS) 0%
4
Monitoring and Control
PGS 32.0 103.0 Jun 17 Dec 11 - 25%
4.1
└ Perform Post-Installation Testing and Safety Inspections
PGS 8.0 1.0 Dec 10 Dec 10 3.10→ (FS+3d) 0%
4.3
└ Document Test Results and Compliance Reports
PGS 8.0 1.0 Dec 11 Dec 11 4.1→ (FS) 0%
4.4
└ Monitor Project Progress Against Schedule and Budget
Sam Chen 8.0 103.0 Jun 17 Dec 11 3.1→ (SS) 50%
4.5
└ Manage Change Requests and Issue Resolution
Sarah Chen 8.0 103.0 Jun 17 Dec 11 3.1→ (SS) 50%
5
Project Closure
Sam Chen 4.0 1.0 Dec 15 Dec 15 - 0%
5.1
└ Finalize and Archive Project Documentation
Sam Chen 2.0 1.0 Dec 15 Dec 15 4.3→ (FS) 0%
5.2
└ Conduct Project Review and Lessons Learned
Sarah Chen 2.0 1.0 Dec 15 Dec 15 4.3→ (FS) 0%